01 — Highways structures
Cascades Bridge and Shore Hill parapet upgrade
The Cascades sits above Ventnor's Eastern Esplanade, one of the busiest stretches of seafront on the Island. For Island Roads, C45 built the new reinforced concrete parapets on the Cascades Bridge and the Shore Hill retaining wall, working for Stoneham Construction to Atkins' design.
- 28 reinforced concrete parapet bays on new bases, many on curves, tight radii, returns and offsets, so most bays were one-offs
- Timber formwork made on site to follow the curve of the existing structure
- Starter bars drilled and fixed into the existing structure to tie the new parapet in
- Worked from a scaffold spanning the esplanade buildings, with public access kept open around the site
- Client
- Island Roads
- Delivered for
- Stoneham Construction
- Design
- Atkins


02 — Sea defences
Marsh Cottage seawall and wave wall
After Storm Eunice damaged the concrete seawall on an exposed headland at Gurnard, C45 rebuilt and upgraded it on a design and build basis with PTR Consulting.
- Temporary works developed with the engineer for a one-sided pour against the sea, on a tight site
- New reinforced concrete wall and curved wave wall, with shutters lifted in by crane and props taken off the existing structure
- Every pour timed to the tide
- Coordinated with the council's coastal engineer and a rock-armour delivery by barge
- Client
- Private
- Basis
- Design and build
- Engineer
- PTR Consulting


03 — Water sector
Southern Water AMP7 treatment works upgrades
Since 2023, C45 has been Galliford Try's delivery partner on the Isle of Wight for Southern Water's AMP7 upgrade programme. We have held a series of NEC subcontracts across four live treatment works at the same time: Sandown, Roud, Calbourne and Shalfleet. The work has been delivered by our own formwork, steel-fixing, concrete and groundworks gangs, while each works stayed in operation.
- Sandown: a new sludge cake bay with around 170m of reinforced concrete retaining wall, poured both sides, on a 930m² reinforced slab — about 295m³ of concrete and 39 tonnes of rebar
- Sandown: 1200mm-diameter deep drainage laid in a sheet-piled, hydraulically framed trench, plus valve slab, pile caps, access road and diversion chamber
- Calbourne: humus tank and retaining wall civils, RC structures and site enabling
- Roud and Shalfleet: main civils packages, generator compound, inlet works and enabling works
- Design changes managed through the NEC contract, priced and agreed from our own site records
- Client
- Southern Water
- Delivered for
- Galliford Try
- Basis
- NEC subcontracts, 2023 to date


Tell us about the job